So Much Progress!

There has been a lot of great progress on the project recently and we have many updates to share. Check out the photos below to see some of the great work being done!

-Scot Grossman, Jefferson County Open Space

IMG_0443

The trail is taking shape near the eastern end of JC-1. Taken on 7/21/14.

IMG_0469

Jefferson County Open Space Trails Specialist Ted Diltz III working on a new set of stairs down to Clear Creek on 8/20/14.

IMG_0470

Trails Specialists Chris Cruz, Tim Roybal, Ted Diltz III and Chad Morger working on a river access point on 8/20/14.

IMG_0488

The 1st temporary river crossing installed on 8/27/14.

IMG_0495

A new section of drape mesh installed at the western end of JC-1. Photo taken on 9/3/14.

 

 

 

 

 

 

IMG_0497

Almost ready for concrete on 9/9/14.

 

 

 

 

 

 

 

 

 

 

IMG_1042

The first piece of concrete in Jefferson County poured on 10/2/14.

 

IMG_0504

Now you can really see it. Taken on 10/7/14.

 

 

 

 

 

 

 

IMG_1117

Seeding the sides of the trail on 10/16/14.

IMG_0536

Swinging in concrete culverts for the 3rd temporary crossing. Taken 10/29/14